Vail roofing code requirements

Vail roofing code reference
Current building code
What this jurisdiction requires
2021 IBC and 2021 IRC
Current energy code
What this jurisdiction requires
2021 IECC
Building permit required
What this jurisdiction requires
Yes
Other or special permits required
What this jurisdiction requires
Approval by design review board needed
Roof system fire rating (residential)
What this jurisdiction requires
Class A required under wildland urban interface amendments
Roof system fire rating (commercial)
What this jurisdiction requires
Class A
Roof system fire rating (multi-family)
What this jurisdiction requires
Class A
Minimum wind speed rating for asphalt shingles
What this jurisdiction requires
115 MPH exposure B ASCE - 2011
Inspectors carry ladders for the final
What this jurisdiction requires
No
Requires midroof (in progress) inspection
What this jurisdiction requires
No
Maximum layers of asphalt shingles permitted
What this jurisdiction requires
One layer
Requires solid sheeting over spaced decking
What this jurisdiction requires
No
Requires drip edge
What this jurisdiction requires
Yes
Minimum drip edge size
What this jurisdiction requires
1 x 2
Requires rake / gable metal edging
What this jurisdiction requires
Yes
Self adhering underlayment (ice and water shield)
What this jurisdiction requires
Ice barrier required at eaves per IRC R905.1.2
Underlayment required 4:12 and above
What this jurisdiction requires
2 layers 15#
Rolled roofing allowed on low slope over living space
What this jurisdiction requires
No
Type of valleys allowed
What this jurisdiction requires
Both
Valley material required for closed valleys
What this jurisdiction requires
Either
Valley material required for open valleys
What this jurisdiction requires
Either
Kick-out required on step flashing
What this jurisdiction requires
Yes
Requires ventilation to meet code
What this jurisdiction requires
Yes

Last checked September 2, 2026. This reflects published sources at that date, not an official ruling. Code adoptions change, so confirm with the Vail building department before you pull a permit.

What Vail requires, in plain language

Vail builds to the 2021 IBC and 2021 IRC. That edition, not the newest code published nationally, is the rulebook an inspector in Eagle County holds your roof to. Energy work on the same permit follows the 2021 IECC.

Layer limit in Vail: One layer. This is the line item that moves a bid the most. If your existing roof is already at the limit, the deck gets stripped before new material goes down, and the labor plus dump fees belong in the written price.

Wind is what Vail tests shingles against. Shingles need a 115 MPH exposure B ASCE - 2011 rating.

Underlayment and edge metal are where roofs fail inspection. Ice and water shield: Ice barrier required at eaves per IRC R905.1.2. On 4:12 and steeper: 2 layers 15#. Drip edge: Yes. Minimum drip edge size 1 x 2.

Vail Town Council approved the 2021 editions of the IBC, IRC, IFC, IECC, IPC and IFGC in May 2022. Wildland urban interface amendments drive the roof covering requirements here.

Installation details above come from our building department field survey for Vail, last updated 1/3/19. Code editions and contacts are refreshed from the department directly. Always confirm the details on your permit before work starts, since departments amend requirements on their own schedule.

Code compliant roof installation near Vail, Colorado

Sources

These links go straight to the jurisdiction, so you always have the real-time source. Adoptions and amendments change on their schedule, not ours. Always confirm before permitting.

Last checked September 2, 2026. This is our best read of published sources, not an official ruling. Confirm with the Vail building department before you pull a permit.

Free inspection, same day answers